• About
    About Donna About Parramatta
  • Community
    Community Campaigns Community Survey Community Wins JP Services Local Community Groups Local Sporting Groups Parramatta Youth Alliance Practical support to help your family budget Report a Pothole School Upgrades Sydney Olympic Park Masterplan 2050
  • News
    Community News Media Releases Speeches
  • Sign up to my Community Newsletter!

Parramatta East Public School

PARRAMATTA EAST PUBLIC SCHOOL UPGRADE

We’re delivering on our commitment to build better schools for NSW.

After a decade of inaction by the previous Liberal National Government, we’re getting on with the job of upgrading Parramatta East Public School!

As the State Member for Parramatta, I have fought for the following:

  • 24 NEW classrooms, 6 shared common areas & 6 large multipurpose areas
  • NEW school library
  • NEW learning support unit with 3 NEW classrooms, a shared common area & multipurpose space
  • Revamping 6 existing classrooms & converting the library to a staff room
  • Removing old demountables to provide more play space for students

Project Progress:

Construction on the new building has moved from working on the structure to internal fit-out since our last update. 

The roof is now on, and solar panels have been installed. External cladding and windows are complete on the eastern and western sides of the building and progressing on the north and south sides. 

Balustrades are being installed to the Level 1 and 2 balconies, downpipes are going in along the northern elevation, and the eastern entry awning slab has been poured with columns installed.  

Inside the building, the walls and ceilings have been covered with plasterboard and painting is progressing on Levels 1 and 2. 

Tiling in the bathrooms is finished on all floors, and workers have started installing fixtures in these wet areas.  Flooring work is underway, with carpet and vinyl currently being installed on the ground floor and the upper levels.

Installation of joinery has started, indoor glass doors are being put in, major equipment has been delivered, and the connection of internal building services has begun.

The outdoor waste enclosure is fully completed, and work on the pump room is moving forward.

Outside the school, public footpath upgrades along Gaggin Street were carried out during the school holidays in July 2026. 

About Donna Contact Donna Community Survey Media Releases Sign up to my Community Newsletter!

Authorised by Donna Davis MP, 96 George St PARRAMATTA NSW 2150. Funded using parliamentary entitlements.